(40 points) See below for the information about this Magic II Project for Seattle Sunfast Inc. managed by the famous project manager Jim Smith.
Create a MS Project file to enter the proved project information, including the general project properties, tasks, duration and predecessors, resources, and resource assignment. Assume that all activities will begin at their early start times and require the number of hours per day indicated in the table below. The project uses a standard working calendar and each worker is available for 8 hours per day. Do not level this project.
Then answer the following question: what resources have been initially over allocated in the project described by the table? Hint: You can make use of aResource Graphand/orResource Usageview in MS Project.
Expert paper writers are just a few clicks away
Place an order in 3 easy steps. Takes less than 5 mins.